I-70 AT ROUTE 201 INTERCHANGE PEL STUDY PUBLIC MEETING

ABOUT THIS SITE

Welcome to the Virtual Public Meeting for the I-70 at Route 201 Interchange Planning and Environment Linkages (PEL) Study. This virtual public meeting features station-by-station displays of study information. This material will be available until October 28, 2026 during the two-week comment period following the in-person public meeting on October 14.

    Check out some of the Virtual Meeting Features:

    Station Displays

    Each of the available displays at the in-person stations is included below.

    Comment Opportunity

    A comment form is available following all of the virtual display information.

    Station 1: Welcome and Introduction

    Welcome!

    Thank you for visiting the I-70 at Route 201 Interchange PEL Study Virtual Public Meeting Webpage, a product of the Pennsylvania Department of Transportation (PennDOT) Engineering District 12-0 and the Federal Highway Administration.

    This virtual meeting will introduce the I-70 at Route 201 Interchange PEL Study.

    View the video below to learn all about the study. Video captions are available - just click the CC/Subtitles button in the video player.

    View the Informational Handout

    Station 2: PEL Study Overview / Transportation Process

    What is a PEL?

    Planning and Environment Linkages (PEL) studies help to shorten project delivery time. They encourage the use of information developed in planning to inform the National Environmental Policy Act (NEPA) process. NEPA requires federal agencies to assess environmental effects before making final decisions on projects that use federal monies.

    The PEL Study must involve interested State, local, Tribes and Nations, and federal agencies as well as the public, and document relevant decisions in a form that is identifiable and available for review during the NEPA scoping process.

    Comprehensive Study

    Combines planning, engineering & environmental studies

    Provides Flexibility

    In the early evaluation and dismissal of alternatives prior to detailed environmental & engineering studies

    Minimizes Duplication

    Uses decisions & analysis to inform future environmental studies

    Encourages Engagement

    Encourages early, meaningful public and agency engagement

    Environmental Stewardship

    Promotes environmental stewardship

    Reduces Delays

    Reduces delays in implementation

    Study Area Map

    The study area includes the I-70/Route 201 Interchange, 2.8 miles of I-70 (Exit 41 to Exit 44), and 1.2 miles of Route 201 (Westmoreland/ Fayette County line to Vance Dei Cas Hwy). It is located in North Belle Vernon Borough and Rostraver Township, Westmoreland County.

    This has been an area of concern for local officials for over 10 years. This study will consider solutions to reduce congestion, support pedestrian mobility, and increase safety at, and around, the I-70/Route 201 Interchange.

    A map of the I-70 at Route 201 Interchange PEL Study project area showing bridges, park and rides, transit stops, and streams.

    Click here to enlarge Study Area Map

    Transportation Process

    Planning & Environment Linkages (PEL) provides a stronger basis to determine Purpose and Need, community concerns, and local priorities for future project(s).

    A graphic of the transportation process with five steps: 1. Collect and Analyze Data. 2. Identify Transportation Problems (Purpose & Need). 3. Develop Solutions (Alternatives). 4. Determine project(s) that can be advanced for further study. 5. Document projects in the PEL report. PennDOT, FHWA, resource agencies, tribes, nations, community stakeholders & general public are involved throughout the process. Text below reads: Using data and alternatives documented in the PEL report, each project will be advanced through PennDOT's project delivery process: Preliminary Engineering/National Environmental Policy Act (NEPA), Final Design, Right-of-Way Acquisition and Utilities, and Construction.

    Click here to enlarge Transportation Process

    Station 3: Existing Roadway and Traffic Conditions

    Existing/Projected Traffic Backups

    The map below illustrates the traffic backups during three peak times of the day in 2025 and compares those with the projected backups for 2055 at the intersection of Pricedale Road and Rostraver Road (Route 201).

    A map of the I-70 at Route 201 Interchange PEL Study project area showing max traffic queues for 2025 and 2055 during AM peak hour, PM peak hour, and Saturday peak hour.

    Click here to enlarge Existing/Projected Traffic Backups

    What is Levels of Service (LOS)?

    LOS A - FREE FLOW

    Low volumes and no delays.

    LOS B - STABLE FLOW

    Speeds restricted by travel conditions, minor delays.

    LOS C - STABLE FLOW

    Speeds and maneuverability closely controlled because of higher volumes.

    LOS D - STABLE FLOW

    Speeds considerably affected by change in operation conditions. High density traffic restricts maneuverability; volume near capacity.

    LOS E - UNSTABLE FLOW

    Low speeds; considerable delay; volume at or slightly over capacity.

    LOS F - FORCED FLOW

    Very low speeds; volumes exceed capacity; long delays with stop-and-go traffic.

    Existing Conditions

    (Based on 2025 counts during busiest traffic hours)

    A map of the I-70 at Route 201 Interchange PEL Study project area showing Level of Service (LOS) at various intersections.

    Click here to enlarge Existing Conditions

    Projected Conditions (2055)

    (Based on forecasted 2055 counts during busiest traffic hours, without improvements)

    A map of the I-70 at Route 201 Interchange PEL Study project area showing Level of Service (LOS) at various intersections.

    Click here to enlarge Projected Conditions

    Roadway Issues

    The study team identified various roadway issues within the study area.

    A map of the I-70 at Route 201 Interchange PEL Study project area showing stopping sight distance, vertical clearance, auxiliary lane length, horizontal radius, ramp left shoulder width, flat grade, steep grade, ramp lane width, cartway width, vertical curve length, median shoulder width, congestion, streams, and pipes.

    Click here to enlarge Roadway Issues

    Crash Locations

    The crash heat map shows the relative frequency of crashes in the 5-year analysis period. Route 201 south of the I-70 interchange is a hot spot for crashes. The complex geometry of the intersections at Vance Dei Cas and Route 201 may create driver confusion.

    A heat map of the I-70 at Route 201 Interchange PEL Study project area showing a range of lower to higher crash frequency areas.

    Click here to enlarge Crash Locations

    Station 4: Environmental Features

    Environmental Features Map

    Within the study area, environmental features are being mapped to provide groundwork for developing improvement concepts that would minimize natural, historic, social, and community impacts while meeting the purpose and need for the study.

    The PEL study will collect and document baseline environmental information to support the evaluation and comparison of improvement concepts as the study progresses. The environmental studies will include wetland and stream assessments, identification of cultural and historic resources, noise considerations, identification of parks and community features, mapping of threatened and endangered species, and other environmental resources and constraints that may influence the development and evaluation of improvement concepts.

    Ultimately, PennDOT will look for ways to avoid, minimize, and mitigate impacts to environmental features.

    A map of the I-70 at Route 201 Interchange PEL Study project area showing limits of disturbance (LOD), points of interest, streams, pipes, delineated wetlands, historic places, parks, and floodways/floodplains.

    Click here to enlarge Environmental Features Map

    Station 5: Draft Purpose and Need

    Draft Purpose

    The purpose of this study is to develop and evaluate alternatives to address roadway and bridge deficiencies of I-70 (from Exit 41 (Route 906) to the bridge carrying I-70 over the W&LE Railroad) while maintaining and/or improving the connectivity of local roadways and pedestrian access.

    The study will also evaluate improvement options along Route 201 to address the safety and mobility needs (for multiple modes of transportation) of that corridor within the study area.

    Draft Need

    Roadway Deficiencies

    Existing roadway configurations contributing to safety concerns within the study area.

    Structure Deficiencies

    Existing deficiencies associated with a few bridges that contribute to safety concerns in the study area.

    Congestion

    High peak hour traffic volumes cause congestion and result in unacceptable Levels of Service (LOS D or E) on the Route 201 roadway and intersections within the study area.

    Safety

    Based on analysis of crashes within the study area, the roadways in the study area perform worse than similar roadways from a safety perspective.

    Modal Interrelationships

    The lack of sidewalks and/or ADA compliant crosswalks along Route 201 create safety issues and poor transit stop connections.

    System Linkage and Mobility

    I-70 within the study area is not consistent with District 12’s I-70 modernization typical section widths. This is considered a secondary need in the study area.

    Station 6: Community Stakeholder Committee & Comment Opportunity

    Community Stakeholder Committee

    A Community Stakeholder Committee will be convened to provide input and feedback to the Study Team and share information and updates with their respective community segments. Committee members will be assigned by the Study Team to ensure that all areas of interest are represented.

    State Elected Officials
    County/Local Government
    Emergency Services
    Education
    Transit
    Local Business & Industry
    Community Facilities
    Residents

    Community members interested in being considered to represent any of the following community stakeholder segments may submit an interest form at this public meeting or by mail before October 28, 2026.

    Click here to complete an interest form.

    Stay in Touch!

    Cristin Covert, P.E.

    PennDOT District 12 
    Project Manager
    Phone: 724-439-7155
    Email: ccovert@pa.gov

    Ty Murcko, P.E.

    McCormick Taylor
    Project Manager
    Phone: 412-923-3935
    Email: tmurcko@mccormicktaylor.com